The industrial shed of the last forty years is one of the most efficient buildings ever designed. Tilt-up concrete or clad steel walls, a steel portal frame, light purlins and a metal roof spanning large distances for very little material. It was built to keep weather off goods at the lowest possible cost.
That efficiency is now being tested. In When the Shed Becomes a Power Station we argued that energy capacity is becoming a primary determinant of industrial value. Much of that capacity is meant to sit on the roof.
Designed for weather, not equipment
Lightweight industrial roofs were typically designed for the loads they needed to carry: their own weight, maintenance foot traffic, wind and, in some places, snow. Additional dead load was often minimal. Solar arrays add weight, change how wind acts on the roof, and concentrate loads at mounting points. On many roofs this is fine. On some it is not, and the difference can only be known by checking the structure and connections.
In Australia, the 2022 National Construction Code required new commercial buildings to keep at least 20 per cent of the roof clear for future solar and to provide switchboard space for solar and batteries. For warehouses it went further: Part B required long-span warehouse roofs to allow for the future structural load of panels. The 2025 edition goes further again by requiring on-site solar on new commercial buildings. None of it reaches back to existing buildings, and most sheds built before 2022 were never designed for the load.
The sheeting clock
Metal roof sheeting has a finite life that depends on coating, environment and maintenance. Coastal and industrial atmospheres shorten it. A solar array installed on sheeting with ten years of life left will have to come off when the roof is replaced, at real cost. The sensible sequence is often roof first, panels second, which can move a roof replacement earlier than condition alone would justify.
Putting a twenty-five-year array on a roof with ten years left is a capital decision, whether or not anyone made it consciously.
Two clocks on one roof
The sequencing problem is a mismatch between two lives. Solar modules commonly carry performance warranties of around 25 years; many roofs under them have far less left.
| Roof | Typical life (years) | Risk under a 25-year array |
|---|---|---|
| Single-ply membrane | 15 to 20 | Likely to need renewal during the array’s life |
| Modified bitumen (torch-on) | 10 to 15 | Will almost certainly need renewal under the array |
| Prefinished metal panels | About 25 | Matched if the roof is new; mismatched if it is halfway through |
| Existing metal roof, 15 years old | About 10 remaining | Removal and reinstatement of the array likely |
Roof lives: Menlo Park Fire Protection District facility condition assessment, Appendix 4. Solar life reflects typical manufacturer performance warranties; coastal and industrial exposure shortens roof life.
The arithmetic favours doing the roof first where its remaining life is shorter than the array’s. Removing and reinstating an array to renew the roof beneath it adds cost, downtime and risk to a job that would have been simpler done in the right order.
Skylights, safety and fire
Older sheds often have translucent roof sheets and skylights that become brittle with age and present a fall hazard. Solar installation means more people on the roof, which brings fall protection, safe access and walkways into scope. Some older industrial roofs in Britain and Australia still carry asbestos cement sheeting, which must not be walked on or drilled without specialist management.
Fire is the other consideration. Arrays add electrical equipment across the roof surface. Insulated panel roofs and walls with combustible cores, used in some buildings, change the fire risk. Insurers and fire authorities increasingly take an interest in how arrays are designed, isolated and accessed.
What the engineer checks
A structural assessment for rooftop solar on an existing shed typically covers five things. The additional dead load of panels and mounting against the design capacity of purlins, rafters and portal frames, including any corrosion loss. Wind effects, since arrays change uplift and can concentrate load at mounting points and roof edges. Connections, which are often the weakest link in light steel roofs. The condition and remaining life of the sheeting the mounts attach to. And the roof’s ability to take the foot traffic and access equipment that installation and maintenance bring.
The outcome is usually one of three: the roof can take the array as designed; it can with local strengthening or a lighter layout; or it should be re-sheeted first and the array designed with the new roof. Knowing which before procurement avoids the common failure of buying an array for a roof that cannot carry it.
Three markets, one roof
The physics is the same in Dandenong, Doncaster and Dallas. The drivers differ. Australian owners of existing sheds face tenant demand, NABERS and the example set by the new-build mandate. British owners face minimum energy standards for letting and grid connection constraints. American owners face local performance standards in some cities and incentive regimes that change with federal and state policy. In all three, the roof is the physical gate, and the register should read it as one system: structure, sheeting, drainage, skylights, access, hazardous materials and the array itself.
Roof first
Read the roof as one system: structure and connections, sheeting and its remaining life, penetrations and drainage, skylights and access, and any hazardous materials. That reading says whether the roof can host solar now, after strengthening, or only after replacement.
It also turns an energy decision into a sequenced capital plan, which is the right place for it. The roof is no longer just weatherproofing. It is part of the building’s energy system.
Sources
Named sources consulted for this paper. Consequential claims link to their source in the text. Reviewed 3 November 2026; next review by 3 November 2027.
- National Construction Code, Australian Building Codes Board. Accessed 3 November 2026.
- Vic first state to go with NCC 2025, Australian Steel Institute. Accessed 3 November 2026.
- NSW and Queensland defer adoption of NCC 2025, HVAC&R News. Accessed 3 November 2026.
- Asbestos, Health and Safety Executive. Accessed 3 November 2026.
- NCC 2025 or NCC 2022: which edition applies in your state, Tilekind, 2026. Accessed 3 November 2026.
- Energy efficiency webinar questions and answers (NCC 2022, J9D5 and warehouse structural loads), Australian Building Codes Board. Accessed 3 November 2026.
- Facility condition assessment, Appendix 4: nominal life expectancy for building components, Menlo Park Fire Protection District. Accessed 3 November 2026.
Questions
How do I know whether a warehouse roof can take solar panels?
A structural engineer should check the roof structure and connections for the additional load and changed wind effects, and the sheeting should be assessed for remaining life. Skylights, access and any hazardous materials also need review.
Should the roof be replaced before installing solar?
If the sheeting is near the end of its life, replacing it first usually avoids removing and reinstalling the array later. The decision depends on remaining sheeting life compared with the expected life of the array.