If the 1970s office was built around its structure and facade, the office of the 1980s and 1990s was built around its services. Larger floor plates, more glass, more equipment, more cooling. Variable air volume systems, centralised chilled water, raised floors for cabling, the first building management systems, faster lifts with electronic controls.

Thirty to forty years on, the structure of most of these buildings is sound. The capital sits in the services and in the systems that keep the envelope sealed.

Second and third cycles

Mechanical plant has shorter lives than structure. Chillers, cooling towers, boilers and air-handling units installed when these buildings opened have often been replaced once and may be approaching a second replacement. Pumps, fans and terminal units follow their own cycles. The question for an owner is rarely whether the plant works today. It is when the next major replacement falls and whether it should be like for like.

Refrigerants add a regulatory layer. Older refrigerants were phased out under international agreements, and newer ones face their own phase-down schedules. Plant that runs on a refrigerant that is becoming scarce becomes more expensive to maintain and may be replaced earlier than its physical condition alone would suggest.

The refrigerant clock

Plant from this generation often runs on refrigerants that are being phased out, and the phase-out dates now drive replacement as much as wear does.

Refrigerant phase-out dates by market
MarketR22 (HCFC)HFCs such as R134a and R410A
AustraliaBulk imports limited to servicing from 2020; banned entirely from 1 January 2030; reclaimed R22 still allowedImports phased down from 2018, reaching 85% below baseline by 2036
United StatesProduction and import ended on 1 January 2020AIM Act phase-down of 85% by 2036
United Kingdom and EUVirgin HCFC banned for servicing from 2010, recycled from 2015F-gas regulation phase-down, with bans on high-warming refrigerants in new equipment

Australian Government R22 and HFC guidance; US and UK dates as enacted. Check current regulations before planning a replacement.

For an owner the effect is practical. A chiller on R22 can still run, but every leak repair draws on a shrinking and dearer supply, and a major failure may make replacement the only economic choice. A chiller on R410A has longer, but its refrigerant is on the same path. Recording the refrigerant against each item of plant, as the plant room reading in this paper suggests, turns a regulatory schedule into a capital one.

The first and second generations of building management systems were proprietary, and many controllers installed in the 1990s and 2000s are no longer supported. Spare parts are scarce, integration with newer plant is difficult, and the system often cannot support the analytics described in What AI Takes Out of the Building.

In this generation, the controls often date the building more than the chillers do.

The envelope relies on sealants

Curtain walls and glazed facades from this era depend on sealants, gaskets and structural glazing compounds that age with sun and movement. A facade can look fine from the street while seals fail, letting water and air in and allowing condensation behind the glass. Facade maintenance programmes, reseal works and, eventually, glazing upgrades are recurring items.

Some buildings of this period, and later, used cladding materials that are now the subject of remediation programmes in Australia and Britain and of tighter code requirements in the United States. Identifying cladding type is part of reading any building from the 1990s onward.

Reading the plant room

The quickest way to read a building of this generation is to walk its plant rooms with a list. For each major item: year installed, refrigerant, hours run, maintenance record, parts availability, and whether the controls that run it are supported. Chillers and cooling towers first, then boilers or heat pumps, air-handling units, pumps and the main switchboard. Then the building management system: who made it, what version, whether the vendor still supports it and whether it can be integrated.

The register that results is usually services-heavy in the two-to-five-year horizon, with the envelope reseal and lift modernisation close behind. The structure rarely appears except where car park concrete or balcony elements are exposed.

The electrification question

Many of these buildings heat with gas boilers and cool with electric chillers. Electrifying heating means replacing boilers with heat pumps that produce lower-temperature water and draw more electrical load, which pushes the question back to the switchboard and supply. For larger let buildings in England and Wales, the expected EPC B standard from 2031 makes this a sequenced programme rather than a choice, and in American cities with performance standards the same works are a compliance path. In Australia the driver is more often NABERS performance, tenant expectation and gas pricing than regulation.

The practical reading is that the plant replacement already due in this generation is also the moment to decide the building’s energy future. Replacing like for like can lock in a second gas cycle. Replacing with electrified plant brings the switchboard and distribution forward. Either way, the decision deserves to be made explicitly.

Lifts and electrical

Lift controllers, drives and door equipment from this period are commonly due for modernisation. Electrical switchboards installed with the building are now old enough that spare capacity, safety features and parts availability matter, especially if the owner wants to electrify heating or add charging. As Energy Becomes a Building Function argues, the main switchboard often gates later decisions.

A services-led plan suits this generation: map the plant, its age, its refrigerant, its controls and its dependencies, then sequence replacements so that each one prepares the building for the next.

Sources

Named sources consulted for this paper. Consequential claims link to their source in the text. Reviewed 3 November 2026; next review by 3 November 2027.

Questions

How long does commercial chiller plant usually last?

Service life varies with type, maintenance and operating conditions, and many chillers are replaced at somewhere around twenty to thirty years. Refrigerant availability and efficiency can justify earlier replacement.

Why do curtain wall facades need resealing?

Sealants and gaskets degrade with UV exposure, temperature cycling and movement. When they fail, water and air can enter even though the facade looks intact, so periodic inspection and resealing are normal maintenance.