Distress present and progressing. Repair programmed for the near term. These are the 126 findings the Technical Library grades as condition, across 103 elements and spaces, each with what it means for timing. Each element’s name opens its own page, where the finding sits with its causes and remedies.

Substructure

Basement, Cellars & Retaining Walls

FindingImpactWhat it means for timing
Seepage, efflorescence, blocked drainage, early rotation3 ImportantRepair in the near term.

Foundations

FindingImpactWhat it means for timing
Seasonal movement causing repeated cracking; decaying stumps3 ImportantAddress causes and repair in the near term.

Slab on Ground

FindingImpactWhat it means for timing
Joint deterioration; curling; moisture-driven flooring failures3 ImportantRepair in the near term.

Sub-floor & Crawlspace

FindingImpactWhat it means for timing
Blocked ventilation; damp; decay starting3 ImportantRepair in the near term.

Superstructure

Load-Bearing Masonry

FindingImpactWhat it means for timing
Early bowing; cracked arches; decaying lintels3 ImportantRepair in the near term.

Structural Core

FindingImpactWhat it means for timing
Corroded bracing connections; minor unengineered penetrations3 ImportantRepair in the near term.

Structural Frame

FindingImpactWhat it means for timing
Corrosion and spalling without significant section loss; ASR; failed car park membranes3 ImportantRepair programme in the near term.

Upper Floor Slabs & Structures

FindingImpactWhat it means for timing
Decking corrosion; notched joists; creep deflection affecting finishes3 ImportantRepair in the near term.

Façades

Architectural & Decorative Features

FindingImpactWhat it means for timing
Active cramp or anchor corrosion cracking units, without displacement; widespread terracotta spalling2 PlannedProgramme re-anchoring and repair in the near term.

Building Maintenance Units (BMU)

FindingImpactWhat it means for timing
Corrosion, wear and leaks at fixings without a failed item3 ImportantRepair in the near term.

Canopies & Awnings

FindingImpactWhat it means for timing
Rod and frame corrosion without movement; cracked masonry around anchorages without displacement2 PlannedRepair in the near term.

Cladding & Wall Systems

FindingImpactWhat it means for timing
Spalling precast from reinforcement corrosion; fixing corrosion without displacement; leaks at windows3 ImportantProgramme repair in the near term; extent from investigation.

External Coating Systems

FindingImpactWhat it means for timing
Widespread peeling, blistering or render debonding without loss; coating failure on steel with spreading rust3 ImportantRepair and recoat in the near term.

Glazing Systems

FindingImpactWhat it means for timing
Widespread gasket shrinkage, failed perimeter seals, IGU failure across an elevation, hardware failing2 PlannedProgramme repair or replacement in the near term.

Masonry/Brickwork

FindingImpactWhat it means for timing
Tie corrosion cracking; lintel corrosion cracking over openings; floor-line bowing on a framed building; cracks 5 to 15 mm; persistent penetrating damp2 PlannedProgramme repair in the near term, ahead of the next façade inspection cycle where one applies.

Sealants & Joints

FindingImpactWhat it means for timing
Failed fire-rated joints at slab edges or through fire-separating walls2 PlannedRepair with a tested system in the near term; it is a fire compliance item.
Widespread adhesive or cohesive failure with no damage yet2 PlannedProgramme replacement in the near term, by elevation.

Verandahs, Balconies & Balustrades

FindingImpactWhat it means for timing
Heavy planters, spas or enclosures on a balcony not designed for them4 EssentialRemove or assess the load before further use.
Post-base corrosion without looseness; membrane leaks without structural damage; fastener corrosion on decks3 ImportantProgramme repair in the near term.

Roofs & Rainwater Goods

Chimney Stacks & Flues

FindingImpactWhat it means for timing
Cracked flaunching; eroded pointing; lifted flashings without leaks3 ImportantRepair in the near term.

Insulation

FindingImpactWhat it means for timing
Mould growth in the roof space or on ceilings from condensation2 PlannedCorrect ventilation and vapour control in the near term.
Gaps and compression across large areas; condensation without damage yet2 PlannedRepair in the near term.
Vermin-infested insulation2 PlannedRemove, clean and replace after pest control.

Plant Screens & Parapets

FindingImpactWhat it means for timing
Open coping joints; cracked masonry without lean; corroded screen bases2 PlannedRepair in the near term.
Parapet too low to serve as edge protection where people work on the roof2 PlannedAdd guardrails before further roof access.

Rainwater Systems

FindingImpactWhat it means for timing
Box gutters or parapet roofs without adequate overflows3 ImportantAdd or enlarge overflows in the near term.
Gutter soles corroding where water stands; poor falls3 ImportantProgramme repair or replacement of the affected runs.
Lead goods stolen; water discharging against the wall3 ImportantReplace the goods (often in a non-lead material) in the near term.

Roof Coverings

FindingImpactWhat it means for timing
Lap and edge corrosion short of perforation3 ImportantProgramme repair or partial replacement in the near term: treat and coat where the metal is intact; replace the lower run above the gutter where it is not.
Condensation corroding sheets from beneath3 ImportantCorrect the cause (vapour control, ventilation) before renewing the covering.
Fixings leaking or backing out3 ImportantReplace failed fixings with oversized screws and new washers.
Loose ridge and hip cappings3 ImportantRebed and repoint the ridges and hips.
Isolated slipped slates3 ImportantRefix or replace the slipped slates; where slippage keeps spreading, plan re-slating with stainless steel or copper nails.

Roof Safety Systems

FindingImpactWhat it means for timing
No rescue plan for a fall arrest system in use4 EssentialPrepare the plan and equipment before the next use.
Fall arrest relied on for frequent routine access3 ImportantAdd collective protection along the routes in the near term.
Corrosion without failure; loose guardrail fixings; rigging plan out of date3 ImportantProgramme repair and update in the near term.

Roof Structure

FindingImpactWhat it means for timing
Cut webs, missing bracing or bridging; corrosion taking section; termite damage short of failure3 ImportantProgramme repair in the near term.
Bracing slack or removed; fly braces missing3 ImportantRestore before the next high-wind season.
Tie-down well below current requirements in a cyclonic or high-wind region3 ImportantUpgrade at the next re-roofing, sooner if exposed.

Skylights, Dormers & Glazed Atria

FindingImpactWhat it means for timing
Embrittled sheets; seals at end of life3 ImportantReplace in the near term.
Condensation dripping onto finishes or stock2 PlannedImprove ventilation, heating or glazing in the near term.

Waterproofing Membranes

FindingImpactWhat it means for timing
Seams opening, details failing, membrane brittle at upstands3 ImportantProgramme detail repairs or recover in the near term.
Membrane splits over structural or deck joints3 ImportantInstall movement joints and repair in the near term.
Later penetrations sealed with mastic only3 ImportantFlash properly at the next roof works.

Internal Areas

Bathrooms & Wet Areas

FindingImpactWhat it means for timing
Cracked grout, failed sealant, weak exhaust, mould3 ImportantRepair in the near term.

Commercial Kitchens

FindingImpactWhat it means for timing
Floor, lining and drainage defects3 ImportantRepair in the near term.

Commercial Office Areas (Base-Build)

FindingImpactWhat it means for timing
Comfort complaints; worn finishes in common areas; fit-out residue affecting services2 PlannedRepair or rebalance in the near term.

Common Circulation Areas

FindingImpactWhat it means for timing
Worn finishes; wall damage; odours2 PlannedRepair in the near term.

Common Internal Areas

FindingImpactWhat it means for timing
Worn finishes; security weaknesses2 PlannedImprove in the near term.

Electrical & Communications Risers

FindingImpactWhat it means for timing
Congestion; overheating; poor labelling3 ImportantImprove in the near term.

Fireplaces

FindingImpactWhat it means for timing
Worn seals and glass4 EssentialRepair.

Flooring

FindingImpactWhat it means for timing
Wear; minor cupping; stains2 PlannedRepair in the near term.

Integrated Building Systems

FindingImpactWhat it means for timing
Cyber exposure; poor documentation3 ImportantImprove in the near term.

Internal Doors & Hardware

FindingImpactWhat it means for timing
Worn hardware, binding doors, heavy doors on accessible routes2 PlannedRepair in the near term.

Internal Stairwells

FindingImpactWhat it means for timing
Worn nosings; missing handrails; dark landings3 ImportantRepair in the near term.

Internal Wall & Ceiling Finishes

FindingImpactWhat it means for timing
Cracking, mould, stained tiles, worn paint2 PlannedRepair in the near term.

Kitchen

FindingImpactWhat it means for timing
Swollen cabinetry; weak extraction; worn appliances2 PlannedRepair or replace in the near term.

Lift Cars & Machine Rooms

FindingImpactWhat it means for timing
Worn interiors; hot cars; accessibility gaps4 EssentialImprove in the near term.

Loading Docks & Goods Handling

FindingImpactWhat it means for timing
Impact damage; slab joints; waste hygiene2 PlannedRepair in the near term.

Lobbies & Atria

FindingImpactWhat it means for timing
Comfort and acoustic problems; worn finishes2 PlannedImprove in the near term.

Main Entrance & Reception Areas

FindingImpactWhat it means for timing
Worn matting and floors; draughts; outdated directories2 PlannedRepair in the near term.

Maintenance Access Areas

FindingImpactWhat it means for timing
Corrosion; missing walkways; poor lighting2 PlannedRepair in the near term.

Partitioning Systems

FindingImpactWhat it means for timing
Acoustic leakage; cracking; damage2 PlannedRepair in the near term.

Plant Rooms

FindingImpactWhat it means for timing
Poor housekeeping; noise; worn floors and coatings3 ImportantImprove in the near term.

Public Amenities

FindingImpactWhat it means for timing
Worn fixtures and finishes; odour; partition damage2 PlannedRepair in the near term.

Residential Units/Guest Rooms

FindingImpactWhat it means for timing
Mould, noise complaints, worn finishes2 PlannedRepair in the near term.

Retail Tenancies (Base-Build)

FindingImpactWhat it means for timing
Service provisions inadequate for current market; make-good shortfalls2 PlannedUpgrade at vacancy or lease renewal.

Service Corridors

FindingImpactWhat it means for timing
Impact damage; hygiene; poor lighting2 PlannedRepair in the near term.

Specialised Occupancy Areas

FindingImpactWhat it means for timing
Worn finishes; acoustic and ventilation shortfalls2 PlannedImprove in the near term.

Specialist & Non-Standard Features

FindingImpactWhat it means for timing
Condensation; ageing plant3 ImportantRepair in the near term.

Storage & Archive Areas

FindingImpactWhat it means for timing
Damp, pests, poor housekeeping2 PlannedImprove in the near term.

External Elements

Ancillary Structures

FindingImpactWhat it means for timing
Decay or corrosion starting; worn shade fabric2 PlannedRepair in the near term.

Fencing, Gates & Signage

FindingImpactWhat it means for timing
Decay, corrosion, worn operators, faded signs2 PlannedRepair in the near term.

Landscaping & Irrigation

FindingImpactWhat it means for timing
Roots affecting drains and paving; bridged damp-proof courses; irrigation overspray2 PlannedAddress in the near term.

Pavements & Hardstand

FindingImpactWhat it means for timing
Cracking, ruts and ponding without failure2 PlannedRepair in the near term.

Recreational Facilities

FindingImpactWhat it means for timing
Worn equipment; court cracking4 EssentialRepair in the near term.

Stormwater Drainage

FindingImpactWhat it means for timing
Sediment build-up; roots; failing devices3 ImportantClean and repair in the near term.

Mechanical Services

Air Handling Units (AHUs)

FindingImpactWhat it means for timing
Outside air below code minimum; failed dampers; corroded drain pans; fouled coils3 ImportantRepair in the near term.

Building Management & Control System (BMCS)

FindingImpactWhat it means for timing
Unsupported controllers and software; drifted sensors; overrides3 ImportantUpgrade and recommission in the near term.

Central Cooling Plant

FindingImpactWhat it means for timing
Rising approaches, recurring leaks, worn pumps, unsupported drives or controls3 ImportantRepair, retube or upgrade in the near term.

Central Heating Plant

FindingImpactWhat it means for timing
Sludge, corrosion, failed expansion vessel, poor combustion3 ImportantRepair and treat in the near term.

Ductwork & Air Distribution

FindingImpactWhat it means for timing
Dirty ductwork, poor balance, torn insulation3 ImportantClean, rebalance and repair in the near term.

Heat Rejection Plant

FindingImpactWhat it means for timing
Corrosion, scale, worn mechanicals3 ImportantRepair in the near term.

Localised HVAC

FindingImpactWhat it means for timing
Coil corrosion, leaks, drain faults3 ImportantRepair in the near term.

Terminal Units

FindingImpactWhat it means for timing
Many units with failed actuators, drifted sensors or blocked drains3 ImportantProgramme in the near term.

Ventilation Systems

FindingImpactWhat it means for timing
Sensors drifting; fans worn; poor balance3 ImportantRepair in the near term.

Electrical Services

Communications, Security & Specialist Systems

FindingImpactWhat it means for timing
Unsupported systems; cyber exposure; coverage gaps3 ImportantUpgrade in the near term.

Emergency Lighting

FindingImpactWhat it means for timing
Batteries failing duration tests across the installation4 EssentialReplace batteries or fittings in the near term.

Emergency Power

FindingImpactWhat it means for timing
Batteries at end of life; fuel contaminated; wet stacking; capacity tight4 EssentialRepair in the near term.

Lighting

FindingImpactWhat it means for timing
Widespread failures; levels below standard3 ImportantRepair and relamp in the near term.

Lighting Control System

FindingImpactWhat it means for timing
Overrides, drift and poor commissioning3 ImportantRecommission in the near term.

Lightning Protection

FindingImpactWhat it means for timing
High earth resistance; corrosion; unbonded plant3 ImportantRepair in the near term.

Main Electrical Supply

FindingImpactWhat it means for timing
Thermographic hot spots; breakers failing tests; unsupported devices; partial discharge3 ImportantRepair in the near term.

Power Distribution

FindingImpactWhat it means for timing
Overheating terminations; unsupported devices; unsealed penetrations; missing schedules4 EssentialRepair in the near term.

Solar Photovoltaic (PV) Systems

FindingImpactWhat it means for timing
Degradation, corrosion, leaks2 PlannedRepair in the near term.

Fire Services

Automatic Sprinkler Systems

FindingImpactWhat it means for timing
Corrosion, MIC, head defects, coverage gaps after fit-outs4 EssentialRepair in the near term.

Fire Detection & Alarm Systems

FindingImpactWhat it means for timing
Contaminated or aged detectors; repeated unwanted alarms; coverage gaps; matrix out of date4 EssentialRepair and recommission in the near term.

Fire Pumping Systems

FindingImpactWhat it means for timing
Performance decline; jockey cycling; battery or fuel issues; tank deterioration3 ImportantRepair in the near term.

Hydrant & Hose Reel Systems

FindingImpactWhat it means for timing
Leaks; seized valves; missing caps; aged hoses3 ImportantRepair in the near term.

Passive Fire Protection

FindingImpactWhat it means for timing
Widespread penetration breaches; walls not to slab; damaged structural protection4 EssentialRemediation programme in the near term.

Portable Fire Equipment

FindingImpactWhat it means for timing
Missing, damaged or depressurised units3 ImportantReplace in the near term.

Smoke Management Systems

FindingImpactWhat it means for timing
Equipment worn; partial interface faults3 ImportantRepair in the near term.

Specialist Suppression Systems

FindingImpactWhat it means for timing
Panel or detection ageing3 ImportantRepair.

Hydraulic Services

Gas Services

FindingImpactWhat it means for timing
Corrosion; unprotected pipes; redundant pipework3 ImportantRepair in the near term.

Hot & Warm Water Plant

FindingImpactWhat it means for timing
Loop below temperature; scale; corroding tanks3 ImportantRepair in the near term.

Pumping Systems

FindingImpactWhat it means for timing
Worn pumps, failed pressure vessels, fouled floats3 ImportantRepair in the near term.

Sanitary & Drainage Systems

FindingImpactWhat it means for timing
Root intrusion, corrosion, displaced joints3 ImportantRepair in the near term.

Specialist Hydraulics

FindingImpactWhat it means for timing
Worn finishes, ageing plant, corroded equipment3 ImportantRepair in the near term.

Trade Waste Systems

FindingImpactWhat it means for timing
Corroded baffles and tank; undersized for current use3 ImportantRepair or upgrade in the near term.

Water Supply

FindingImpactWhat it means for timing
Galvanised corrosion, recurring copper leaks, dezincification, seized valves, high pressure3 ImportantRepair in the near term.

Vertical Transportation

Accessibility Lifts

FindingImpactWhat it means for timing
Worn drives, failing batteries, corrosion at an external unit3 ImportantRepair in the near term.
No maintenance contract in place3 ImportantPut one in place now.
Unit works but users cannot operate it independently4 EssentialFix controls, keys, call points and signage.

Dock Levellers & Goods Hoists

FindingImpactWhat it means for timing
Hydraulic leaks, deck drift, worn bumpers, broken pit edges, failed dock seals3 ImportantRepair in the near term.
No maintenance regime for the goods hoists; no free-fall testing record3 ImportantPut a regime in place now.

Escalators & Moving Walks

FindingImpactWhat it means for timing
Chain and roller wear short of the limit; handrail wear; noisy drives; water in the pit3 ImportantRepair in the near term.
Maintenance delivered below the contracted scope3 ImportantEnforce or re-tender now.

Passenger & Goods Lifts

FindingImpactWhat it means for timing
Rising breakdowns, worn doors, rope wear approaching discard criteria, hydraulic leaks3 ImportantRepair or modernise in the near term.
Maintenance delivered below the contracted scope3 ImportantEnforce or re-tender the contract now.

Building Code Compliance

Disabled Access (DDA)

FindingImpactWhat it means for timing
Heavy doors, faded contrast, missing signage, accessible toilets misused3 ImportantFix in the near term.

Hazardous Materials

FindingImpactWhat it means for timing
Bonded asbestos weathering; lead paint flaking4 EssentialManage or remove in the near term.

Occupational Health & Safety (OHS)

FindingImpactWhat it means for timing
Worn stairs, faded signs, ageing treatments4 EssentialRepair in the near term.

Environmental

Electric Vehicle (EV) Charging

FindingImpactWhat it means for timing
Unmetered charging; poor load management; ageing chargers2 PlannedImprove in the near term.

Energy Efficiency Upgrades

FindingImpactWhat it means for timing
Upgrades underperforming; savings drifting2 PlannedRecommission in the near term.

Sub-metering

FindingImpactWhat it means for timing
Mapping errors; ratio and polarity faults; data gaps2 PlannedCorrect in the near term.

Water Conservation

FindingImpactWhat it means for timing
Leaks, timed urinals, poor tower control2 PlannedFix in the near term.